Key Dates of the Installation Programme
All dates are provisional as at 13 March
24 March 2003 | Enter Albion Dry Dock |
28 March | Create access by removing funnel casing and part of promenade deck |
4 April | Renew upper cowl of funnel |
8 April | Removal of Newbury Sirron engines |
14 April | Refitting of funnel casing (the new engines are smaller and will require smaller access) |
18 April | Installation of gearboxes |
5 May | Undocking |
9 May | Installation of Grenaa engines |
13 May | Refitting of Promenade Deck |
20 May | Sea trials |
22 May | Vessel due Glasgow |