Key Dates of the Installation Programme

All dates are provisional as at 13 March

24 March 2003 Enter Albion Dry Dock
28 March Create access by removing funnel casing and part of promenade deck
4 April Renew upper cowl of funnel
8 April Removal of Newbury Sirron engines
14 April Refitting of funnel casing (the new engines are smaller and will require smaller access)
18 April Installation of gearboxes
5 May Undocking
9 May Installation of Grenaa engines
13 May Refitting of Promenade Deck
20 May Sea trials
22 May Vessel due Glasgow