Main Engine L. P. cylinder cover laid out for inspection by MCA Surveyor. Sitting on top is one of the piston rings and the spring set which maintains the piston ring seal in the cylinder.

Main Engine L. P. slide valve cover, shot blasted, prime coated and awaiting survey.

Main Engine L. P. piston with piston ring and junk ring sitting on top, again blasted, primed and ready for survey.

Main Engine I. P. valve assembly shown in two halves, ready for survey.

I. P. piston rod metalic packing assembly set out for survey.

I. P. ahead and astern valve eccentric rods, cleaned, polished and set out for survey.

All three ahead/astern drag links cleaned polished and set out for survey.

Various ship’s valves and valve chests, both steam and water, fully refurbished, surveyed, pressure tested and set aside for fitting back into Waverley.