PADDLE STEAMER WAVERLEY
HERITAGE REBUILD DIARY
Supported by and
Summary Work Programme as at 29 July 2000 Please note that the following is a simplified summary showing some key elements from the detailed programme.
|
PROGRESS REPORTS
29 November 1999 |
Waverley Steam Navigation Co Ltd announced that the contract for the Heritage Rebuild had been awarded to George Prior Engineering Ltd of Great Yarmouth. |
18
- 21 December 1999 |
P.S.
Waverley sails from temporary lay-up at Avonmouth to Great Yarmouth. |
9
January 2000 |
|
11
January 2000 |
|
14
January 2000 |
|
17
January 2000 |
|
18
January 2000 |
|
24
January 2000 |
|
25
January 2000 |
|
27
January 2000 |
|
1
February 2000 |
|
8
February 2000 |
|
16
February 2000 |
|
24
February 2000 |
|
29
February 2000 |
|
1
March 2000 |
|
8
March 2000 |
|
14
March 2000 |
|
15
March 2000 |
|
15
March 2000 |
|
22
March 2000 |
|
23
March 2000 |
|
4
April 2000 |
|
13
April 2000 |
|
18
April 2000 |
|
20
April 2000 |
|
27
April 2000 |
|
28
April 2000 |
New starboard sponson
house being fitted - new after deck shelter being fabricated
|
29
April 2000 |
|
10
May 2000 |
|
11
May 2000 |
|
15
May 2000 |
|
16
May 2000 |
|
26
May 2000 |
|
3
June 2000 |
|
4
June 2000 |
|
5
June 2000 |
|
7
June 2000 |
|
20
June 2000 |
|
|
|
5
July 2000 |
|
|
|
|
|
21
July 2000 |
Ian
McMillan, Project Director, said "There is a lot of work still to be
done, but nobody has said to me it won't be done on time and I'm not
expecting them to." |
24
July 2000 |
|
27
July 2000 |
|
29
July 2000 |
|
2
August 2000 |
|
7
August 2000 |
|
11
August 2000 |
|
12
August 2000 |
|
15
August 2000 |
|
16
August 2000 |
Chief Photographer and
Project Manager Gordon Reid stands beneath Waverley's paddle wheels. Picture by Nick James |
|